Por favor, use este identificador para citar o enlazar este ítem:https://uvadoc.uva.es/handle/10324/64897
Título
Project risk management from the bottom-up: Activity Risk Index
Autor
Año del Documento
2020
Editorial
Springer
Descripción
Producción Científica
Documento Fuente
Central European Journal of Operations Research, 2021, 29, 1375–1396
Resumen
Project managers need to manage risks throughout the project lifecycle and, thus, need to know how changes in activity durations influence project duration and risk. We propose a new indicator (the Activity Risk Index, ARI) that measures the contribution of each activity to the total project risk while it is underway. In particular, the indicator informs us about what activities contribute the most to the project’s uncertainty so that project managers can pay closer attention to the performance of these activities. The main difference between our indicator and other activity sensitivity metrics in the literature (e.g. Cruciality, Criticality, Significance, or Schedule Sensitivity Indices) is that our indicator is based on the Schedule Risk Baseline concept instead of on cost or schedule baselines. The new metric not only provides information at the beginning of the project, but also while it is underway. Furthermore, the ARI is the only one to offer a normalized result: if we add its value for each activity, the total sum is 100%.
Palabras Clave
Activity Risk Index; Schedule Risk Baseline; Sensitivity analysis; Schedule risk analysis; Project control
ISSN
1435-246X
Revisión por pares
SI
Version del Editor
Propietario de los Derechos
(c) Todos los derechos Springer
Idioma
spa
Tipo de versión
info:eu-repo/semantics/publishedVersion
Derechos
restrictedAccess
Aparece en las colecciones
Ficheros en el ítem