RT info:eu-repo/semantics/article T1 On the project risk baseline: Integrating aleatory uncertainty into project scheduling A1 Acebes Senovilla, Fernando A1 Poza Garcia, David Jesús A1 González Varona, José Manuel A1 Pajares Gutiérrez, Javier A1 López Paredes, Adolfo K1 Total project risk K1 Riesgo total de proyecto K1 Aleatory uncertainties K1 Incertidumbres aleatorias K1 Risk baseline K1 Línea base de riesgos K1 Project scheduling K1 Programación de proyectos AB Obtaining a viable schedule baseline that meets all project constraints is one of the main issues for project managers. The literature on this topic focuses mainly on methods to obtain schedules that meet resource restrictions and, more recently, financial limitations. The methods provide different viable schedules for the same project, and the solutions with the shortest duration are considered the best-known schedule for that project. However, no tools currently select which schedule best performs in project risk terms. To bridge this gap, this paper aims to propose a method for selecting the project schedule with the highest probability of meeting the deadline of several alternative schedules with the same duration. To do so, we propose integrating aleatory uncertainty into project scheduling by quantifying the risk of several execution alternatives for the same project. The proposed method, tested with a well-known repository for schedule benchmarking, can be applied to any project type to help managers to select the project schedules from several alternatives with the same duration, but the lowest risk. PB Elsevier SN 0360-8352 YR 2021 FD 2021 LK https://uvadoc.uva.es/handle/10324/48154 UL https://uvadoc.uva.es/handle/10324/48154 LA eng NO Computers & Industrial Engineering, 2021, vol. 160, 107537 NO Producción Científica DS UVaDOC RD 01-jun-2024