Beyond Earned Value Management: A Graphical Framework for Integrated Cost, Schedule and Risk Monitoring
Autor
Año del Documento
2013
Editorial
Elsevier
Documento Fuente
Procedia - Social and Behavioral Sciences, March 2013, 74, 181-189
Zusammenfassung
In this paper, we propose an innovative and simple graphical framework for project control and monitoring, to integrate the dimensions of project cost and schedule with risk management, therefore extending the Earned Value methodology (EVM). EVM allows Project managers to know whether the project has overruns (over-costs and/or delays), but project managers do not know when deviations from planned values are so important that corrective actions should be taken or, in case of good performance, sources of improvement can be detected. From the concept of project planned variability, we build a graphical methodology to know when a project remains “out of control” or “within expected variability” during the project lifecycle. To this aim, we define and represent new control indexes and new cumulative buffers. Five areas in the chart represent five different possible project states. To implement this framework, project managers only need the data provided by EVM traditional analysis and Monte-Carlo simulation. We also explore the sensitivity of the methodology to control variables.
Palabras Clave
Earned Value Management; risk management; project control and monitoring
ISSN
1877-0428
Revisión por pares
SI
Patrocinador
This research has been financed by the project “Computational Models for Strategic Project Portfolio Management”, supported by the Regional Government of Castile and Leon (Spain) with grant VA056A12-2.
Idioma
spa
Tipo de versión
info:eu-repo/semantics/draft
Derechos
openAccess
Aparece en las colecciones
Dateien zu dieser Ressource