Título
Is Something Missing from Project Risk Management? Correlation Matters
Año del Documento
2026-02-03
Editorial
Springer Nature
Descripción
Producción Científica
Documento Fuente
Data Science, Challenges and Applications for Industrial Innovation and Sustainability. CIO 2025. Lecture Notes on Data Engineering and Communications Technologies, vol 280. p. 21-26
Abstract
In this paper, we show that correlations between the durations of project activities can change the project’s total variance and some risk sensitivity indexes such as the Cruciality (CrI) and SSI (Schedule Sensitivity Index). These results are relevant in project risk management as correlations may change risk response strategies, and monitoring efforts should focus on other activities. We performed Monte Carlo simulations using different network topologies with different characteristics.
ISSN
2367-4512
Revisión por pares
SI
Patrocinador
This project has been partially funded by the Regional Government of Castille and Leon (Spain), under the Regional Accredited Research Groups Support Program, with grant VA042G24.
Version del Editor
Propietario de los Derechos
Springer Nature
Idioma
spa
Tipo de versión
info:eu-repo/semantics/submittedVersion
Derechos
embargoedAccess
Aparece en las colecciones
Files in questo item