<?xml version="1.0" encoding="UTF-8"?><?xml-stylesheet type="text/xsl" href="static/style.xsl"?><OAI-PMH xmlns="http://www.openarchives.org/OAI/2.0/" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.openarchives.org/OAI/2.0/ http://www.openarchives.org/OAI/2.0/OAI-PMH.xsd"><responseDate>2026-04-28T19:07:08Z</responseDate><request verb="GetRecord" identifier="oai:uvadoc.uva.es:10324/84254" metadataPrefix="edm">https://uvadoc.uva.es/oai/request</request><GetRecord><record><header><identifier>oai:uvadoc.uva.es:10324/84254</identifier><datestamp>2026-04-21T19:21:33Z</datestamp><setSpec>com_10324_1180</setSpec><setSpec>com_10324_931</setSpec><setSpec>com_10324_894</setSpec><setSpec>col_10324_1375</setSpec></header><metadata><rdf:RDF xmlns:rdf="http://www.w3.org/1999/02/22-rdf-syntax-ns#" xmlns:doc="http://www.lyncode.com/xoai" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xmlns:ore="http://www.openarchives.org/ore/terms/" xmlns:dcterms="http://purl.org/dc/terms/" xmlns:ds="http://dspace.org/ds/elements/1.1/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:edm="http://www.europeana.eu/schemas/edm/" xsi:schemaLocation="http://www.w3.org/1999/02/22-rdf-syntax-ns# http://www.europeana.eu/schemas/edm/EDM.xsd">
<edm:ProvidedCHO rdf:about="https://uvadoc.uva.es/handle/10324/84254">
<dc:creator>Pajares Gutiérrez, Javier</dc:creator>
<dc:creator>Acebes Senovilla, Fernando</dc:creator>
<dc:creator>Martín Cruz, Natalia</dc:creator>
<dc:creator>Gúdel, Ricardo</dc:creator>
<dc:date>2026-04</dc:date>
<dc:description>Producción Científica</dc:description>
<dc:description>This paper analyses the impact of correlations between activity durations on project uncertainty and risk sensitivity indexes using Monte Carlo simulation. Results show that correlations have little effect on expected project duration but significantly affect variance and sensitivity measures, especially cruciality (CrI) and SSI, while criticality (CI) remains relatively stable. The effects are strongly moderated by network topology, particularly Project Tightness (PT), which emerges as a key factor explaining the magnitude of these changes.</dc:description>
<dc:format>application/pdf</dc:format>
<dc:identifier>https://uvadoc.uva.es/handle/10324/84254</dc:identifier>
<dc:language>spa</dc:language>
<dc:title>The Role of Correlations Between Activity Durations in Project Schedule Risk Analysis</dc:title>
<dc:type>info:eu-repo/semantics/article</dc:type>
<edm:type>TEXT</edm:type>
</edm:ProvidedCHO>
<ore:Aggregation rdf:about="https://uvadoc.uva.es/handle/10324/84254#aggregation">
<edm:aggregatedCHO rdf:resource="https://uvadoc.uva.es/handle/10324/84254"/>
<edm:dataProvider>UVaDOC. Repositorio Documental de la Universidad de Valladolid</edm:dataProvider>
<edm:isShownAt rdf:resource="https://uvadoc.uva.es/handle/10324/84254"/>
<edm:isShownBy rdf:resource="https://uvadoc.uva.es/bitstream/10324/84254/1/The%20Role%20of%20Correlations_pms2026.pdf"/>
<edm:provider>Hispana</edm:provider>
<edm:rights rdf:resource="http://creativecommons.org/licenses/by-nc-nd/4.0/"/>
</ore:Aggregation>
<edm:WebResource rdf:about="https://uvadoc.uva.es/bitstream/10324/84254/1/The%20Role%20of%20Correlations_pms2026.pdf">
<edm:rights rdf:resource="http://creativecommons.org/licenses/by-nc-nd/4.0/"/>
</edm:WebResource>
</rdf:RDF></metadata></record></GetRecord></OAI-PMH>