Impact of aleatoric, stochastic and epistemic uncertainties on project cost contingency reserves
Autor
Año del Documento
2022
Editorial
Elsevier
Descripción
Producción Científica
Documento Fuente
International Journal of Production Economics, 2022, vol. 253, 108626
Abstract
In construction projects, contingency reserves have traditionally been estimated based on a percentage of the total project cost, which is arbitrary and, thus, unreliable in practical cases. Monte Carlo simulation provides a more reliable estimation. However, works on this topic have focused exclusively on the effects of aleatoric uncertainty, but ignored the impacts of other uncertainty types. In this paper, we present a method to quantitatively determine project cost contingency reserves based on Monte Carlo Simulation that considers the impact of not only aleatoric uncertainty, but also of the effects of other uncertainty kinds (stochastic, epistemic) on the total project cost. The proposed method has been validated with a real-case construction project in Spain. The obtained results demonstrate that the approach will be helpful for construction Project Managers because the obtained cost contingency reserves are consistent with the actual uncertainty type that affects the risks identified in their projects.
Palabras Clave
Cost contingency
Costo de contingencia
ISSN
0925-5273
Revisión por pares
SI
Patrocinador
Junta de Castilla y Leon (grant VA180P20)
Propietario de los Derechos
© 2022 The Authors
Idioma
eng
Tipo de versión
info:eu-repo/semantics/publishedVersion
Derechos
openAccess
Aparece en las colecciones
Files in questo item
La licencia del ítem se describe como Attribution-NonCommercial-NoDerivatives 4.0 Internacional